How to build a PPM schedule across multiple sites

A good planned preventative maintenance (PPM) schedule starts with an accurate asset register, sets each task's frequency from law, standards and manufacturer guidance, then spreads the work across the year so every site is covered without overloading contractors.

By the Fabric FM teamUpdated 30 October 20268 min read

Key points

  • A PPM schedule is only as good as the asset register behind it. Build that first, site by site.
  • Set frequencies in this order: law and standards, manufacturer instructions, industry guidance such as SFG20, then your own failure history.
  • SFG20 classifies tasks by criticality: statutory, business critical, optimal and discretionary. Use the same idea to prioritise your own schedule.
  • Spread tasks across the calendar so contractors visit evenly and trading is not disrupted.
  • Track completion by site, task type and contractor, and close out remedial work, not just the visit.

What a PPM schedule is for

Planned preventative maintenance is work done on a schedule to keep assets safe, legal and working, before they fail. A PPM schedule is the list that drives it: every asset, every task, how often and by whom.

For a multi-site operator it does three jobs. It proves you are meeting statutory duties at every site. It reduces breakdowns that close a kitchen or a counter. And it gives you a basis for budgeting and for holding contractors to account.

The schedule is not the same as a compliance calendar, although it includes one. It also covers the routine tasks that keep equipment running, such as cleaning condensers, changing filters and checking gaskets.

Step 1: build the asset register

You cannot schedule maintenance on assets you have not recorded. For each site, list every maintainable item. At a minimum capture:

  • Asset ID that is unique across the estate, ideally on a label on the asset.
  • Asset type using a consistent naming list (for example "Espresso machine, 2-group" rather than free text).
  • Make, model and serial number, needed for parts and manufacturer guidance.
  • Location within the site (kitchen, bar, plant room, roof).
  • Install date and warranty expiry.
  • Owner: owned, leased, landlord's or supplier's. This decides who is responsible for maintaining it.
  • Statutory flags, such as gas appliance, pressure system or lifting equipment.
Walk the site

Desk-based registers miss things. Do a physical walk-round of each site with a checklist by area, photograph data plates and confirm what is actually there. Repeat it whenever a site is refitted.

Do not forget building services that sit outside the operator's day-to-day view: water tanks and calorifiers, roof plant, extract fans, fire dampers, emergency lights and the distribution board. In leased premises, check the lease to see which of these the landlord maintains.

Step 2: use SFG20 and other standards to set tasks

SFG20 is the industry standard library of maintenance specifications for building services in the UK, published by BESA. It gives task lists and frequencies for a wide range of asset types and is widely referenced in FM contracts.

SFG20 classifies each task by criticality. The categories are:

SFG20 classificationMeaningHow to treat it
Statutory / legal (red)Work required by lawNon-negotiable. Track to the day and keep evidence.
Business critical (pink)Not required by law, but critical to your operation or contractTreat almost as strictly as statutory work.
Optimal (amber)Function-critical or industry best practicePlan and do, but can flex within reason.
Discretionary (green)Non-critical, optionalDo when it pays back, or bundle with other visits.

SFG20 is a subscription product, and it covers building services rather than every piece of catering equipment. For items like espresso machines, combi ovens and dishwashers, use the manufacturer's service schedule alongside it. For statutory tasks, go back to the source: the regulation, HSE guidance or the relevant British Standard.

Step 3: set frequencies you can defend

Work through each asset in this order and record the reason for the frequency you choose:

  1. Law and standards. For example, BS 5839-1 for fire alarm servicing, BS 5266-1 for emergency lighting, HSE ACOP L8 and HSG274 for legionella control, PSSR 2000 for pressure systems, and the F-gas regulations for leak checks.
  2. Manufacturer instructions. These often set the minimum to keep a warranty valid.
  3. Industry guidance. SFG20, BESA TR19 Grease for kitchen extract, and trade body guidance.
  4. Your own data. Usage hours, failure history and environment. A site trading 18 hours a day works its equipment harder than one trading 8.
Risk-based intervals

Some guidance gives a range or says the interval should be set by risk assessment. In that case, do not quote a single number as if it were law. Record the assessment, the interval chosen and when you will review it.

A sample PPM template for a café or restaurant site

Below is a starting template for a typical café or small restaurant with a commercial kitchen. Adjust it for your equipment, your lease and your own risk assessments. Frequencies shown are common practice or set by the cited standard. Where they depend on risk or usage, the table says so.

AssetTaskFrequencyStatutory?Typical contractor
Gas cooking appliances and supplyService and gas safety inspectionAnnually (common practice)Yes: duty to maintain under the Gas Safety (Installation and Use) Regulations 1998Gas Safe registered engineer (commercial catering)
Kitchen extract systemDuctwork and canopy grease cleaning to TR19 GreaseBy usage: typically 3, 6 or 12 monthsFire safety duty; insurer requirementSpecialist extract cleaner
Kitchen extract filtersClean or replace canopy filtersWeekly or more often if heavy useSupports fire safetySite team
Fire alarm systemWeekly call point test; serviceWeekly test; service at least every 6 months (BS 5839-1)Yes: Fire Safety Order 2005Site team; fire alarm contractor
Emergency lightingMonthly function test; annual full-duration testMonthly and annually (BS 5266-1)Yes: Fire Safety Order 2005Site team; electrical contractor
Fire extinguishersBasic serviceAnnually (BS 5306-3)Supports Fire Safety Order dutiesFire equipment contractor
Hot and cold water outletsSentinel outlet temperature checksMonthly (HSG274), as set by your risk assessmentYes: legionella duties under COSHH and ACOP L8Site team or water hygiene contractor
Espresso machinePreventative service; written scheme examination where it is a pressure systemService per manufacturer and usage; examination per written scheme (PSSR 2000)Examination yes, where PSSR appliesCoffee machine engineer; competent person
Espresso machine water filterReplace cartridgeBy litres treated and water hardnessNoCoffee machine engineer
Refrigeration (fridges, freezers, cold room)Clean condensers, check seals and temperaturesQuarterly typical; daily temperature logsLeak checks only where above F-gas thresholdsRefrigeration engineer (F-gas certified)
Air conditioningService; F-gas leak check where applicableService 6–12 monthly typical; leak checks by CO2-equivalent chargeF-gas leak checks yes, where thresholds applyF-gas certified engineer
Fixed electrical installationEICRUp to 5 years, or as the last report recommendsElectricity at Work Regulations 1989 dutyElectrical contractor
Portable appliancesIn-service inspection and testingRisk-based (IET Code of Practice)Duty to maintain; no fixed intervalElectrical contractor or trained staff
Dishwasher / glasswasherService, descale, check rinse temperaturePer manufacturer; typically 6–12 monthlyNoWarewashing engineer
Grease trapEmpty and cleanBy size and volumeDrainage and water company requirementsDrainage contractor

For detail on the kitchen items, see our commercial kitchen compliance checklist and the guide to espresso machines and PSSR.

Step 4: spread the work across the calendar

Once every site has a task list, the next problem is timing. If every annual task across fifty sites is due in January, contractors will be stretched, standards will slip and site managers will be fed up.

  • Stagger annual tasks by site, for example by region or by month of opening.
  • Group tasks by contractor and site, so one visit covers several jobs.
  • Avoid peak trading such as December for hospitality, or term-time lunch service for school caterers.
  • Plan out-of-hours work for tasks that need isolations, like EICRs and extract cleaning.
  • Leave a tolerance window, for example two weeks either side, and agree it in the contract. Statutory tasks should not be allowed to drift past their due date.

Build your calendar 12 months ahead and review it quarterly. When a site opens, closes or refits, update its register and schedule straight away.

Step 5: track completion and close the loop

A PPM schedule is a plan. You need evidence that the plan happened. For every task, track:

  • Date due, date attended and whether it was on time.
  • Outcome: pass, fail or remedial work needed.
  • The certificate or service report, attached to the asset.
  • Any remedial job raised and when it was closed.

Report PPM completion by site, by task type and by contractor each month. Separate statutory tasks from the rest so a high overall rate cannot hide a missed gas or fire alarm check. Look for repeat failures on the same asset; they may mean the frequency is wrong or the asset needs replacing.

A visit is not a fix

A common gap is counting a PPM visit as complete when the engineer found a defect that was never repaired. Make remedial work a tracked job with its own deadline, and only treat the asset as compliant when it is closed.

Fabric FM is being built to run this cycle across many sites: one asset register, schedules generated from templates, and certificates and remedials linked to each visit. If that sounds useful, see our planned preventative maintenance software page and join early access.

This guide is general information, not legal advice. Check the current regulations and guidance, or speak to a competent person, for your premises.

FAQs

Common questions

What is a PPM schedule?

A planned preventative maintenance schedule lists every maintainable asset at a site, the tasks each one needs, how often, and who carries them out. It turns legal duties and manufacturer guidance into dated jobs.

What is SFG20?

SFG20 is the UK industry standard library of building maintenance specifications, published by BESA. It sets out tasks and frequencies for thousands of asset types and classifies tasks by criticality, from statutory to discretionary.

How do I decide PPM frequencies?

Start with any legal or standard requirement, then the manufacturer's instructions, then industry guidance such as SFG20. Adjust for how hard the asset works and its failure history, and record why you chose each frequency.

Should every site have the same PPM schedule?

Use a standard template by site type so tasks and frequencies are consistent, but build each site's schedule from its own asset register. Equipment, usage and building services vary even between similar sites.

What is a good PPM completion rate?

Aim for every statutory and safety-critical task to be completed on time. For other tasks, set a target, track it monthly by site and contractor, and investigate patterns of missed or late visits.